Skip to content
PageSpeed 100 as the delivery default
Planung

How Long Does a New Website Take? A Realistic Plan

How long does a new website really take? Seven phases with time frames, the three classic bottlenecks and a go-live window that avoids the Friday risk.

15 min read ZeitplanProjektablaufLivegangDomainumzug

The question about timing comes up in almost every first conversation, usually right after the question about price. It is harder to answer, because the answer depends less on the build than on the input. A modest company website is technically assembled in a few days; getting it live still routinely takes six to ten weeks. That gap almost never opens up at the keyboard. It opens up while waiting for photos, for sign-off and for access credentials. This article lays out the schedule: seven phases with realistic time frames, clear ownership, and a note on what typically blocks each one. Plus the three bottlenecks that explain nearly every delay in practice, a go-live window that does not cost anyone their evening, and seasonal planning that keeps the launch out of the busiest week of the year.

Nine weeks to a new websiteSeven phases, clear ownership — and the three points where things stallSources: DENIC, Bitkom, BFSGTypical schedule of a website projectClient input dueBuild in progressGo-liveWeek1234567891 Preparation and briefing5 days2 Structure and first draft9 days3 Copy and photos17 days4 Legal, consent, access10 days5 Test: mobile and keyboard7 days6 Domain move and go-live3 days7 Follow-up and first review10 daysGo-liveThe three classic bottlenecksPhotos are missingNo shots of the actual business,no rights to third-party images.Often costs two to three weeks.Sign-off without an ownerFour opinions, nobody deciding.Every extra round adds days.One named approver is enough.Access granted too lateAuth code valid 30 days (DENIC).DNS often sits with the old provider.Sort it out four weeks ahead.

Why a website project rarely stalls on the build

Anyone drafting a schedule thinks in working days first: how long does it take to assemble pages, place copy, set up forms? That calculation is not wrong, it is merely incomplete. What matters is not working time but elapsed time — the span from the first conversation to a website people can reach. In a typical project the two differ by a factor of two to three: roughly fifteen to twenty actual working days spread across six to ten calendar weeks (project experience). The difference is waiting time, and waiting time almost always has the same cause: a contribution from the business is missing, or a decision is.

That is a description, not an accusation. A company website has long been standard in Germany: 94 percent (Bitkom, Digitalisation of the Skilled Trades) of trade businesses use one to be visible online, and 88 percent (Bitkom, Digitalisation of the Skilled Trades) add entries in online directories. At the same time 62 percent (Bitkom, Digitalisation of the Skilled Trades) see a concrete need to act on digitalisation, and 75 percent (Bitkom, Digitalisation of the Skilled Trades) struggle with a shortage of skilled staff. The same report explicitly names a lack of time, high costs and uncertainty around new technology as barriers (Bitkom, Digitalisation of the Skilled Trades); it is based on telephone interviews with 504 (Bitkom, Digitalisation of the Skilled Trades) trade businesses. People who are already short of time do not produce copy and photos on the side in the evening. A schedule that fails to account for this is fiction from day one.

The second cause is external pressure. 85 percent (Bitkom, Digitalisation of the Skilled Trades) of businesses observe a clear customer expectation of constant availability, and 89 percent (Bitkom, Digitalisation of the Skilled Trades) find that individual offers are expected. That is exactly why the new website is supposed to go live "as soon as possible" — and exactly why deadlines emerge that nobody can meet. Whether the investment pays off at all and how to tell is covered in the article on when a new website pays off. This one deals with the question that follows: once the decision is made, how long does it take?

Scope: schedule, not redirect engineering

This article covers dates, phases and ownership. How old addresses are technically mapped onto new targets during a move — inventory, status codes, redirect chains, sitemap and canonicals — is covered in the article on a relaunch without ranking loss. The two belong together, but the technical planning needs more room than a schedule can give it.

The seven phases at a glance

Every website project breaks down into seven phases. They do not run neatly one after another; they overlap — copy is already being written while the structure settles, and final corrections run while testing is under way. The order is still binding, because each phase supplies a precondition for the next. Skipping phase three and pushing on to phase six only moves the problem to the point where it is most expensive: just before go-live.

Seven phases, seven time frames

  1. Preparation and briefing — 3 to 5 days

    The business clarifies what the site is meant to achieve: enquiries, appointment requests, applications, or explaining an offer that needs consultation. Add services, audiences, catchment area, existing material and the name of the person who signs off at the end. Without that name, phase two starts with a built-in defect.

  2. Structure and first draft — 5 to 10 days

    Site structure, navigation, a rough build of every page, first visual direction. The result is a draft you can walk through with placeholders, rather than a slideshow of design mockups. This phase sits almost entirely on the build side and is therefore easy to plan.

  3. Copy and photos — 10 to 20 days

    The real bottleneck. Copy has to come from the business or at least be checked for accuracy, and photos have to be taken or legally cleared. This phase derails schedules more often than all the others combined.

  4. Legal pages, consent and accessibility — 5 to 10 days

    Imprint and privacy notice matching the actual business, a cookie banner only where one is genuinely needed, plus contrast, labels, alternative texts and operability. Runs in parallel with phase three once the structure is settled.

  5. Testing on mobile and keyboard — 3 to 7 days

    Every page on a real phone, every function once using the keyboard alone. Submit the form, check the confirmation, tap the phone number, proofread the map and opening hours. The test is short — the corrections that follow are not always.

  6. Domain move and go-live — 1 to 3 days

    The switch itself is the shortest step and the least forgiving. Run-up: lower the TTL, verify access, secure email forwarding, choose the slot deliberately. Go-live takes minutes; propagation across the network takes hours.

  7. Follow-up with fixes and a first review — 10 to 14 days

    Two weeks of observation: broken addresses, form submissions, the first search queries, feedback from the team. Then a short review of what is actually being opened — and what should be cut or added.

In total that gives a frame of roughly six to ten weeks for a modest company website of eight to fifteen pages (project experience). Which pages belong there and which can be skipped is covered in the article on the pages a business website needs. Larger undertakings — several locations, several languages, an extensive service catalogue — mainly push phases two to four back, not go-live itself.

Who supplies what — and what blocks it

A schedule without ownership is a wish list. It pays to reduce every phase to three questions: what comes from the business, what happens on the build side, and what does progress hang on when things stall? The overview below is deliberately plain — it does not replace project planning, but it answers the question of whose turn it is at the next status call.

PhaseFrom the businessTypical blockerTime frame
Preparation and briefingGoals, services, audience, catchment area, a named decision-makerNobody owns it; the briefing is cut short with "that's fine"3 to 5 days
Structure and first draftFeedback on the site structure within two to three daysStructure is torn up again after the copy phase5 to 10 days
Copy and photosSubject matter, price statements, references, imagery with cleared rightsPhotos are missing; copy sits with three people at once10 to 20 days
Legal pages, consent, accessibilityLegal name, register data, tools in use, the person responsible for data protectionDetails are copied from an old site and no longer accurate5 to 10 days
Testing on mobile and keyboardTwo or three people who genuinely test for an hourTesting happens only on the office desktop, never on a phone3 to 7 days
Domain move and go-liveAccess to domain administration, auth code, a list of mailboxesCredentials sit with the previous provider and nobody asked1 to 3 days
Follow-up and reviewFeedback from daily use, additions, correctionsAfter go-live nobody looks at it for two months10 to 14 days

Note the third column: five of the seven blockers are organisational, not technical. That matches what happens in practice — the build is waiting, the business is not being held up. Going through this overview together before the start and entering one name and one date per row shortens elapsed time noticeably more than any speed-up on the build side. What such a sequence looks like in practice is shown step by step in how a website project runs.

The single most effective measure

One name and one date per row. Not "the team", not "next week" — one person allowed to sign off, and one date when the material arrives. That single table replaces half of all status meetings.

The three classic bottlenecks

Delays look random case by case; in aggregate they are not. Across many projects, nearly all of them trace back to three causes. They show up in varying order, but they show up — and all three can be defused before the project starts, once you know them.

Missing or weak photos

The most common reason a finished website sits in draft for three weeks. No shots of the actual business, no rights to the existing material, no date booked for new ones.

Sign-off without an owner

Four opinions, nobody responsible. Every additional review round costs days without measurably improving the content.

Access obtained too late

Domain administration, DNS settings and, for a registrar transfer, the auth code. Sorting this out in phase six burns days at the point with no slack.

Bottleneck one: there are no usable photos

Photos are where most schedules tip over. The pattern usually runs the same way: at the briefing, images are said to be "plentiful". During the copy phase it turns out they are phone shots of building sites against the light, a group picture from the 2019 Christmas party, and a handful of images whose origin nobody can reconstruct. Then the real work starts: planning new shots, finding a date when the premises look presentable and the team is on site, and, if need be, waiting for better weather. Two to three weeks is realistic for that, and none of it appears in a schedule drawn up before the briefing.

The second half of the problem is legal. Imagery from an old website cannot automatically be reused if the licence was tied to the previous service provider. Photos of employees need consent, which does not arrive bundled with the employment contract. Third-party premises, client sites and identifiable people in the background each have their own rules. Which subjects carry a site and what to watch legally is described in detail in the article on photos and image rights on your website. For the schedule, one consequence is enough: the photo question belongs in week one, not week five.

  • Book the date for new photography during the briefing, not later — the calendar is usually the constraint, not the camera
  • Draw up a shot list in advance: team, exterior, work in progress, two or three finished results, vehicle or workshop
  • Obtain consent from the people shown before the images go onto the website
  • Clarify the origin and licence of every legacy image; when in doubt, drop it rather than hope
  • Book a fallback date for outdoor shots — rain is a planning factor, not an exception
  • Until the new images arrive, keep working with placeholders instead of pausing the copy phase

Bottleneck two: sign-off without a named decision-maker

The second bottleneck is less visible and works more slowly. It appears when sign-off goes to a group instead of a person. A text goes to the managing director, to the office manager, to the foreman and to the son-in-law who "knows about the internet". Four responses arrive at four different times, two of them contradict each other, one never comes. Every round costs two to four working days, and after the third round the text is not better, only more cautious. Across a whole project that typically adds one to two extra weeks (project experience) without any work having been done.

A website does not improve because more people comment on it, but because one person decides and the others contribute.

A working rule from project practice

The remedy is unspectacular: one person is named as the decision-maker, collects feedback internally and returns a single, binding version. Feedback gets a deadline — three working days is a common value. Anything arriving after that moves into the follow-up phase, not the current round. And there is a cap: two revision rounds per page. Agreeing these rules up front feels blunt when written down and saves three weeks of discussion later.

Bottleneck three: domain and DNS access, auth code included

The third bottleneck is the most treacherous, because it strikes right at the end — at the point with the least slack. The website is finished, the date is set, and then it turns out nobody knows where the domain is administered. The previous provider registered it "along the way", the credentials sit in a mailbox that no longer exists, and the contact is on holiday that week. The numbers show how ordinary this situation is: in June 2026 the number of registered .de domains passed the 18 million mark (DENIC); statistically that is almost one .de address for every sixth resident of Germany (DENIC). Every single one has an administrator — the only question is whether you know who it is.

When the registrar changes, the auth code comes into play, known as AuthInfo for .de domains. The current provider generates it on the domain holder's instruction and transmits it to the registry in encrypted form; the new provider submits it together with the transfer request (DENIC). The point that matters for the schedule: the code expires automatically after 30 days (DENIC) and then has to be requested again. Request it too early and then push go-live back six weeks, and you apply for it a second time — with the same wait at the old provider. Request it too late and you are waiting in the middle of the go-live window. The sensible corridor is roughly four weeks before the planned date. How domain, mailboxes and forwarding fit together in general is explained in the article on domain and business email basics.

Four questions that need answers four weeks ahead

Who is the registered domain holder — the business or a service provider? Which provider handles administration, and who has an active account there? Where are the DNS records maintained, and who is allowed to change them? And finally: which mailboxes and forwarding rules hang off the same domain? Those four answers cost half an hour at the start. At the end they cost a week.

Choosing the go-live window

Go-live is technically the shortest step of the entire project — and the only one where a mistake is visible immediately. That is why it deserves its own window with a run-up. The most important preparatory step is lowering the TTL: every DNS record carries a validity period telling other servers how long they may remember the answer. If that value is set to 24 hours, some visitors will still see the old website for a full day after the switch. Lowering the TTL to a few minutes 24 to 48 hours before the date shortens that window considerably — and it is raised back to its original value a few days after go-live.

  1. 48 hours before: set the TTL of the affected DNS records to a low value and test access to DNS administration one last time
  2. 24 hours before: document every mailbox, forwarding rule and MX record — a screenshot or export, not from memory
  3. The day before: have the list of existing addresses and their new targets ready so redirects take effect immediately after the switch
  4. On the day, in the morning: make the switch, then check the home page, two subpages, the form and the phone number yourself
  5. Within the first hour: send a test message to a mailbox on the domain and have receipt confirmed
  6. After 24 hours: check again that certificate, redirects and mail delivery are stable, then restore the TTL

No go-live on a Friday afternoon

The rule sounds obvious and is broken regularly all the same. A go-live needs several hours of observation, and observation needs people who are reachable — in the business, at the hosting provider, at the domain registrar. From Friday lunchtime onwards both are scarce. A Tuesday or Wednesday morning slot leaves two full working days of response time before anyone heads into the weekend. The same applies to the days before public holiday bridges, company shutdowns or the holiday of the only person holding the credentials.

The second point regularly overlooked at go-live is email. Domain and mailboxes hang off the same DNS records; thinking only about the website during the switch can make mailboxes unreachable without anyone noticing straight away — incoming messages then go nowhere and the sender gets an error message at best. So MX records and every forwarding rule should be documented before the switch and tested after it. The test is simple: a message from outside to every active mailbox, and a reply back.

Third: old addresses need a destination. When pages get new paths, links from directories, trade articles, email signatures and printed material run into nothing — and printed material cannot be corrected retroactively. The mapping of old to new addresses should exist before go-live and take effect with the switch, not a week later. How that mapping is built properly is covered at length in the article on relaunching without ranking loss; for the schedule it is enough to know the list must be finished the day before.

Seasonal planning: when a go-live sits well

A schedule is not only a question of weeks but also of months. A new website pays off when enquiries arrive — and enquiries are seasonal. At the same time, the input from the business needs exactly the calm that peak season does not offer. Together that yields a simple rule of thumb: go-live sits best shortly before demand rises, with the project phase before it in the quieter period. Reverse the two and you get a website nobody maintains and photos nobody takes.

SectorGood go-live windowUnfavourableReason
Heating and plumbing tradesLate summer to early autumn, before the heating seasonIn the middle of the heating seasonEnquiries rise with the first cold spell; contributions are no longer feasible then
Restaurants with outdoor seatingLate winter to spring, before the terrace seasonHigh summerMenu, opening hours and reservations need to be in place before the rush
Medical practices and health professionsLate spring to early summerFlu season in winterDuring infection season there is not a minute to spare for sign-off and photo shoots
Clubs and voluntary organisationsSix to eight weeks before the general meetingThe week of the meeting itselfThe meeting is a good occasion to present the new site — not to finish it
Landscaping and garden constructionWinter to early springApril to JuneThe order peak coincides with the building season; winter leaves time for content
Consultancies, law and tax firmsLate summer or autumnYear-end and filing deadlinesDeadlines tie up exactly the people who have to check the copy for accuracy

One uncomfortable but useful consequence follows from this table: when the window gets tight, postponing beats pushing through. A go-live under pressure produces exactly the mistakes that cost weeks afterwards — half-finished copy, untested forms, forgotten redirects. A launch delayed by four weeks costs four weeks. A botched launch costs trust, and trust cannot be scheduled. Slack is therefore not a sign of poor planning but part of it: two weeks of reserve on a ten-week project is a realistic approach (project experience).

One day, one week, three months

"How fast can it be in the best case?" is a fair question, and it has three different answers depending on what is already prepared. The decisive difference is not the speed of the build but the state of the input. Starting on Monday with finished copy, cleared image rights and working domain access puts you in a completely different position from someone who still has to decide what the home page should say.

Doable in a day

A single, honest presence page: services in bullet points, a way to get in touch, opening hours, directions, imprint and privacy notice. Precondition: the details exist and the domain is accessible. That is not a stopgap but a base that holds — as long as it is not sold as a finished website.

Doable in a week

A small website of five to eight pages, provided copy exists at least in draft, usable photos are available and one person can sign off at short notice. Legal pages, consent and a test on a phone are part of it. What is missing after that week is polish, not substance.

Needs three months

Several locations or language versions, an extensive service catalogue, new photography, coordinated legal texts across multiple entities, a move involving many legacy addresses. Here the time sits in coordination and input, not in the build.

One warning belongs with every fast option: speed must not come at the cost of load time. 53 percent (Think with Google) of mobile visits are abandoned when a page takes longer than three seconds to load. How strongly that plays out is shown by a case study from a European car manufacturer: improving Largest Contentful Paint by one second went along with 14 percentage points (Google web.dev, Renault case study) fewer bounces and 13 percent (Google web.dev, Renault case study) more conversions; the analysis covered more than ten million visits across 33 countries (Google web.dev, Renault case study). A website built in a day that loads in four seconds is not a time saving. What role usability on small screens plays here is described in the article on mobile usability for business websites.

How to spot an unrealistic schedule

Unrealistic schedules are rarely malicious. Mostly they arise because input from the business does not appear as a work package but as a given. A few warning signs are visible at first glance at the plan — regardless of who drew it up.

  • Input from the business does not appear in the plan at all, only the build steps
  • There is no date for photography, although nobody can claim usable images exist
  • Sign-off appears without names: "client reviews" instead of "Ms Meier signs off by Friday"
  • Legal pages, consent and accessibility show up as the last item before go-live rather than as their own phase
  • Go-live falls on a Friday, right before a company shutdown, or in the week of the annual accounts
  • No separate step is planned for domain and DNS access, although the domain sits with the previous provider
  • There is not a single day of slack between the last correction and go-live
  • The plan ends at go-live — follow-up, corrections and a first review are missing entirely

The cross-check in one sentence

For any schedule, ask which line describes work by the business. If the answer is "none", it is not a schedule but a quote with a date on it.

The process in five steps — and which phases get shorter

Not all seven phases are equally unavoidable. Part of the effort exists because the same foundations get rebuilt in every project: a sensible site structure, a set of legal pages, a consent mechanism, fast delivery, a usability check. When those building blocks are prepared, the schedule does not shift because the work happens faster, but because entire waiting periods disappear. At XICflow the process therefore looks like this:

Services, audience, catchment area, tone of voice and a named decision-maker. This replaces the classic briefing and usually takes one session rather than one week.

What disappears is not the responsibility of the business but the waiting time between phases. Photos, factual accuracy and sign-off remain the company's job — no tool changes that. What changes is the order: instead of waiting six weeks for a draft and then supplying content, the draft comes first and the input flows straight into it. How the three usual routes — website builder, agency, AI-assisted build — differ in effort and ownership is compared in the article on website builder, agency or AI; how that affects cost and duration is shown in the overview of plans.

Legal pages and accessibility do not belong at the end

Since 28 June 2025 the requirements of the German Accessibility Strengthening Act have applied to electronically provided services in consumer business; micro-enterprises with fewer than ten employees and no more than two million euros in annual turnover are exempt for services (German Accessibility Strengthening Act). Whether an exemption applies should be checked legally in case of doubt. For the schedule, one thing holds regardless: adding contrast, labelling and keyboard operation afterwards takes longer than designing them in from the start. The background is explained in the article on the Accessibility Strengthening Act for businesses; the mandatory details themselves are covered in the article on imprint and privacy notice.

That leaves the item that is hardest to plan and still belongs in every schedule: the follow-up. Two weeks after go-live it becomes clear which pages are actually opened, which form submissions arrive and where visitors drop off. Those two weeks are not leftover work but the project's first meaningful feedback. Anyone who wants to see how varied finished results can look will find different sectors and structures among the example websites; the building blocks behind them are shown in the overview of features. For open scheduling questions about a specific project, direct contact is the quickest route.

Sources and studies

This article is based on data from: DENIC eG — statistics on .de, passing the mark of 18 million registered .de domains in June 2026 and the provider transfer procedure using AuthInfo (valid for 30 days); Bitkom e. V. — study report "Digitalisation of the Skilled Trades", telephone survey of 504 trade businesses in Germany (94 percent with their own website, 88 percent with directory entries, 62 percent seeing a need to act on digitalisation, 75 percent facing a skills shortage, 85 percent reporting expectations of constant availability); Think with Google — "Mobile speed: every second counts" (53 percent abandonment rate above three seconds of load time); Google web.dev — Renault case study on optimising Largest Contentful Paint (one second of improvement, 14 percentage points fewer bounces, 13 percent more conversions, more than ten million visits analysed across 33 countries); German Accessibility Strengthening Act (BFSG) — requirements for electronically provided services since 28 June 2025, including the exemption for micro-enterprises. Own experience from website projects is also included and marked as (project experience).